Crown Hill Pump - Tank System

2 Documents in Project

Summary

SCH Number
2015051035
Lead Agency
Ventura County Waterworks District 8
Document Title
Crown Hill Pump - Tank System
Document Type
NOD - Notice of Determination
Received
Posted
10/5/2015
Present Land Use
Vacant / RE-10,000 sf / Existing Community

Document Description
The Ventura County Waterworks District No. 8 (District) is proposing the Crown Hill Pump-Tank System Project to provide a higher elevation tank and increase water storage serving the Santa Susana Knolls neighborhood (Knolls). The proposed facilities are: Crown Hill Pump Station - Two pump units, each rated at 300 gpm, 110 feet lift, and 10 horsepower; Crown Hill Tank - One welded-steel tank with a diameter of 72 feet, a height of approximately 36 feet, a storage capacity of 1 million gallons, a high-water elevation (HWE) of 1490 feet, and a pad elevation of 1458 feet; Water Line - 1,100 feet of 8-inch water line; Pressure Reducing Station - An interconnection between the proposed Crown Hill Tank (HWE 1490 feet) and the existing Alta Vista Tanks (HWE 1404 feet) allowing hydraulic interoperability.

Contact Information
Lauren Funaiole
City of Simi Valley
2929 Tapo Canyon Road
Simi Valley, CA 93063

Phone : (805) 583-6772

Location

Cities
Simi Valley
Counties
Ventura
Cross Streets
Crown Hill Drive, Lyon Place
Zip
93063
Total Acres
.86
Parcel #
646-0-161-060; 646-0-161-070
State Highways
Hwy 118
Railways
UPRR
Waterways
Arroyo Simi
Other Location Info
Santa Susana Knolls

Notice of Determination

Approving Agency
City of Simi Valley
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
2929 Tapo Canyon Road, Simi Valley, CA 93063

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA