Mitigated Negative Declaration for the Eastern Service Area Secondary Connection Project

4 Documents in Project

Summary

SCH Number
2015051031
Lead Agency
Padre Dam Municipal Water District
Document Title
Mitigated Negative Declaration for the Eastern Service Area Secondary Connection Project
Document Type
NOD - Notice of Determination
Received
Posted
10/8/2015
Present Land Use
Single Family Residential / Mobile Home; Commercial and Office; Transportation, Communications, and Utilities; Agriculture
Document Description
The District proposes to excavate a five foot by six foot trench in Los Coches Creek to install a new 20" diameter water supply pipeline under Los Coches Creek. After installation, the trench would be backfilled with the excavated sediment and re-contoured to pre-construction topography. No vegetation will be impacted. The impact will be temporary and 0.004 acre and 10 linear feet.

Contact Information

Name
Mike Porter
Agency Name
RWQCB - San Diego Region
Contact Types
Lead/Public Agency

Location

Cities
El Cajon
Counties
San Diego
Cross Streets
I-8 Business / El Dorado Parkway to Pecan park Lane / Rios Canyon Road
Zip
92021
Total Acres
38
Parcel #
398-290-27, 398-290-31
State Highways
I-8
Schools
Rios & Lakeview ES
Waterways
Los Coches Creek, Lake Jennings
Township
15S
Range
1E
Other Location Info
Lakeside

Notice of Determination

Approving Agency
RWQCB - San Diego Region
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes