Mitigated Negative Declaration for the Eastern Service Area Secondary Connection Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2015051031
- Lead Agency
- Padre Dam Municipal Water District
- Document Title
- Mitigated Negative Declaration for the Eastern Service Area Secondary Connection Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/8/2015
- Present Land Use
- Single Family Residential / Mobile Home; Commercial and Office; Transportation, Communications, and Utilities; Agriculture
- Document Description
- The District proposes to excavate a five foot by six foot trench in Los Coches Creek to install a new 20" diameter water supply pipeline under Los Coches Creek. After installation, the trench would be backfilled with the excavated sediment and re-contoured to pre-construction topography. No vegetation will be impacted. The impact will be temporary and 0.004 acre and 10 linear feet.
- Contact Information
-
Mike Porter
RWQCB - San Diego Region
Lead/Public Agency
2375 Northside Drive
San Diego, CA 92108
Phone : (619) 521-3967
Location
- Coordinates
- 32°50'26"N 116°53'12"W
- Cities
- El Cajon
- Counties
- San Diego
- Cross Streets
- I-8 Business / El Dorado Parkway to Pecan park Lane / Rios Canyon Road
- Zip
- 92021
- Total Acres
- 38
- Parcel #
- 398-290-27, 398-290-31
- State Highways
- I-8
- Schools
- Rios & Lakeview ES
- Waterways
- Los Coches Creek, Lake Jennings
- Township
- 15S
- Range
- 1E
- Other Location Info
- Lakeside
Notice of Determination
- Approving Agency
- RWQCB - San Diego Region
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- Padre Dam Municipal Water District, 9300 Fanita Parkway, Santee, CA 92071
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.