Interim Remedial Measures Work Plan for Cherry Aerospace

3 Documents in Project

Summary

SCH Number
2015051026
Lead Agency
California Department of Toxic Substances Control (DTSC)
Document Title
Interim Remedial Measures Work Plan for Cherry Aerospace
Document Type
NOD - Notice of Determination
Received
Posted
7/2/2015
Present Land Use
light industrial use
Document Description
The California Department of Toxic Substances Control (DTSC) has approved an Interim Remedial Measures Work Plan (IRMWP) submitted by CDM Smith on behalf of Cherry Aerospace. The proposed project consists of a total of 32 wells and an aboveground treatment system to treat extracted groundwater via advanced oxidation processes and air stripper followed by discharge to publicly owned treatment works (POTW) via existing sanitary lines. Off-gas created during the treatment and the extracted soil vapor from the soil vapor extraction system will be treated via vapor-phase granular activated carbon system to contain and adsorb volatile organic compounds (VOCs) and zeolite impregnated with potassium permanganate to oxidize contaminants prior to discharge to atmosphere in accordance with local air quality permit requirements. Upon completion of construction activities, remediation systems operations and maintenance and groundwater monitoring will occur. As a future potential contingency, three injection wells may be installed in upgradient locations northeast of the Main Building and focused Dual Phase Extraction wells could be installed at select locations containing significant COPC mass in the shallow groundwater in order to enhance mass removal at the Solvent Storage Area and Chemical Warehouse.

Contact Information

Name
Chia Rin Yen
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Santa Ana
Counties
Orange
Cross Streets
S. Evergreen Street
Zip
92705
Total Acres
15.5
Parcel #
016-150-009
State Highways
Hwy 405
Railways
SPRR
Township
5
Range
9
Section
30
Base
15.58

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes