French Bar Road at South Fork Jackson Creek Bridge (26C0035) Replacement Project
5 Documents in Project
Summary
SCH Number
2015042036
Lead Agency
City of Jackson
Document Title
French Bar Road at South Fork Jackson Creek Bridge (26C0035) Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
6/26/2015
Present Land Use
Placer County right-of-way; Residential Single Family, Residential, Commercial
Document Description
The City of Jackson intends to replace the existing French Bar Road Bridge (26C-0035) over South Fork Jackson Creek to improve roadway safety and comply with the American Association of State Highway and Transportation Officials (AASHTO) guidelines. The overall 36 ft wide replacement structure will accommodate two approximately 10-ft traffic lanes, two 3-ft shoulders, a 6-ft wide sidewalk on the south side of the bridge, and 2-ft wide standard metal bridge railing barriers on both sides of the bridge. The new bridge abutments will be realigned to provide improved hydraulic capacity through the project area. The new bridge will be raised approximately 3 ft to comply with Caltrans Standards.
Contact Information
Name
Mike Daly
Agency Name
City of Jackson
Contact Types
Lead/Public Agency
Address
Phone
Location
Coordinates
Cities
Jackson
Counties
Amador
Cross Streets
State Highway 49
Total Acres
1.697
Parcel #
Various
State Highways
State Hwy 49 & 88
Schools
Jackson ES
Waterways
S. Fork Jackson Creek, Jackson Creek, Jackass Gulch
Township
6N
Range
11E
Section
28
Base
MDB&M
Notice of Determination
Approving Agency
City Council City of Jackson
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.