Willow Hill Reservoir Multi-Use Trail

3 Documents in Project

Summary

SCH Number
2015032010
Lead Agency
City of Folsom
Document Title
Willow Hill Reservoir Multi-Use Trail
Document Type
NOD - Notice of Determination
Received
Posted
5/1/2015
Present Land Use
Open Space
Document Description
The City of Folsom proposes to construct a new multi-use natural earthen trail within the City of Folsom. The trail will be approximately 2 miles long and 6 feet wide and will be constructed by volunteers using hand tools and a small bobcat (such as a Bobcat 570 MINI). A single-span bridge will be constructed over the riparian area near the west end of the project (Figure 2). The bridge will be approximately 60 feet long and 6 feet wide with concrete abutments. The bridge will be made of pressure-treated wood and is proposed to be assembled onsite. This project has incorporated design features to avoid potential environmental impacts.

Contact Information

Name
Jim Konopka
Agency Name
City of Folsom
Contact Types
Lead/Public Agency

Location

Cities
Folsom
Counties
Sacramento
Cross Streets
Iron Point Road between East Bidwell Street and Prairie City Road
Zip
95630
Total Acres
1
Parcel #
072-1190-multi; 072-3120-multi
State Highways
Hwy 50
Schools
Folsom lake High
Waterways
Alder Creek
Township
9N
Range
8E
Section
7
Base
MDB&M

Notice of Determination

Approving Agency
City of Folsom
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes