Avenue 116 Canal Expansion Project
4 Documents in Project
Summary
SCH Number
2015031029
Lead Agency
Pixley Irrigation District
Document Title
Avenue 116 Canal Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
12/15/2015
Present Land Use
Agriculture
Document Description
The proposed project objectives are to construct three underground pipelines to connect over 800 acres of farmland currently not being served with surface water from the Avenue 116 Canal within the Pixley Irrigation District. The project will include a 20 acre recharge basin to ensure excess water will be returned to groundwater.
Contact Information
Name
Dan Vink
Agency Name
Pixley Irrigation District
Contact Types
Lead/Public Agency
Phone
Location
Counties
Tulare
Cross Streets
South of Avenue 116, East of Rd 140, West of Rd 152, North of Ave 108
Total Acres
1.5 linear miles
Waterways
Deer Creek Channel
Township
22S
Range
25E
Section
23
Base
MDBM
Other Location Info
Pixley
Notice of Determination
Approving Agency
Pixley Irrigation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes