Lateral Pipelines and On-Farm Connections Project

14 Documents in Project

Summary

SCH Number
2015022067
Lead Agency
Sacramento Regional Sanitation District
Document Title
Lateral Pipelines and On-Farm Connections Project
Document Type
NOD - Notice of Determination
Received
Posted
1/14/2021
Present Land Use
This is a regional project with varied land use; however, it can be generally described as rural, agricultural land
Document Description
Harvest Water (formerly the South County Ag Program) includes expanding Regional San's recycled water system to serve agricultural uses in south Sacramento County. The effects of Harvest Water were analyzed in an EIR that was certified in 2017. The Lateral Pipelines and On-Farm Connections Project, which was analyzed at a program-level in the EIR, includes the installation of new distribution mains, service connection laterals, and appurtenant facilities. Construction would begin as early as 2022 and continue for approx. 2 years. As supported by the Initial Study Checklist, Regional San has determined that the project would be within the scope of the certified EIR.

Contact Information

Name
Gayleen Darting
Agency Name
Sacramento Regional County Sanitation District
Contact Types
Lead/Public Agency

Name
Agency Name
Same as lead agency
Contact Types
Project Applicant

Location

Counties
Sacramento
Regions
Northern California, Unincorporated
Other Location Info
south Sacramento County

Notice of Determination

Approving Agency
Sacramento Regional County Sanitation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print