Harvest Water Pipeline System (Streambed Alteration Agreement EPIMS Notification No. SAC-17233-R2) Amendment #2

14 Documents in Project

Summary

SCH Number
2015022067
Lead Agency
Sacramento Area Sewer District (SASD)
Document Title
Harvest Water Pipeline System (Streambed Alteration Agreement EPIMS Notification No. SAC-17233-R2) Amendment #2
Document Type
NOD - Notice of Determination
Received
Posted
6/7/2024
Document Description
Amendment #2 added new work locations within the existing Agreement’s project limit due to refinement in the design process, including on-farm connection assemblies, additional staging areas, contractor turn-arounds, and work area for a portion of the SacSewer/ Rio Cosumnes Correctional Center Force Main pipe that conveys wastewater to the EchoWater Resource Recovery Facility that will be installed in a parallel trench at the same time as the Harvest Water pipeline. There were five changes to culvert work which include; removing work at one culvert location, including two culverts that were missed at a previous culvert location, and correcting culvert sizes. The Permittee name was changed from Sacramento Regional County Sanitation District to Sacramento Area Sewer District (SacSewer) and the existing Agreement was transferred to SacSewer. There were also changes to impact classifications resulting in increased permanent habitat impacts, while there was a reduction in temporary habitat impacts, which affect the amount of mitigation required.

Contact Information

Name
Harvey Tran
Agency Name
CALIFORNIA DEPARTMENT OF FISH &WILDLIFE
Job Title
Senior Environmental Scientist (Specialist)
Contact Types
Responsible Agency

Location

Cities
Elk Grove
Counties
Sacramento
Regions
Northern California
Other Location Info
Generally located throughout the City of Elk Grove and unincorporated areas of southwestern Sacramento County; Occurring at 26 watercourses including but not limited to Franklin Creek, the Erhardt Channel, Stone Lake Creek, the Lambert Canal, and unnamed tributaries

Notice of Determination

Approving Agency
CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
CDFW's Regional Office

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.