American River Pipeline Conveyance Project
6 Documents in Project
Summary
SCH Number
2015022027
Lead Agency
Carmichael Water District
Document Title
American River Pipeline Conveyance Project
Document Type
NOD - Notice of Determination
Received
Posted
12/9/2015
Present Land Use
Sacramento County - Residential (R2); City of Rancho - Parks and Open Space (POS), Residential (R5)
Document Description
The Central Valley Regional Water Board is issuing a 401 Water Quality Certification for the subject Project. The project consists of: 1) removing the existing culvert and replacing it with a bottomless culvert; 2) installing a new pipe to carry water from the north bank of the American River to the south bank; 3) removing the existing, antiquated pipe from the American River; 4) creating a stairstepping drainage pool facility as a transition from the new culvert to the low flow bank of the American River; and 5) removing two unused steel and concrete vaults on the northern bank of the American River.
Contact Information
Name
Stephanie Tadlock
Agency Name
Central Valley Regional Water Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Rancho Cordova
Counties
Sacramento
Cross Streets
Rossmoor Drive and Coloma Road
Zip
95670
Total Acres
4
Parcel #
USGS: Citrus Heights, Carmichael
State Highways
Hwy 50
Railways
No
Airports
No
Schools
Williamson ES
Waterways
American River
Township
9N
Range
6E
Base
MDB&M
Other Location Info
Carmichael
Notice of Determination
Approving Agency
Central Valley Regional Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.