Final EIR for the Beverly Hills High School, Hawthorne K-8 School, and El Rodeo K-8 School Improvement Project

4 Documents in Project

Summary

SCH Number
2015021038
Lead Agency
Beverly Hills Unified School District (BHUSD)
Document Title
Final EIR for the Beverly Hills High School, Hawthorne K-8 School, and El Rodeo K-8 School Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2015
Present Land Use
Institutional-Government, S School
Document Description
The Beverly Hills Unified School District is proposing improvements at Beverly Hills High School, Hawthorne K-8 School, and El Rodeo K-8 School to rehabilitate the existing structures at each campus through architectural upgrades, seismic upgrades, mechanical upgrades, electrical upgrades, technological upgrades and plumbing upgrades. Additionally, the proposed project includes the demolition of some buildings and construction of new buildings, as well as new perimeter fencing for additional security and access control. The proposed project also includes modifications to existing and new athletic facilities, and new parking facilities. Finally, hazardous materials, primarily asbestos and lead paint are in many of the buildings and will be removed, as well as soil contamination at BHHS and El Rodeo, as part of the proposed project. The proposed project will not result in an increase in the student, faculty or staff population beyond that of the current design capacity of the schools.

Contact Information

Name
Steven Kessler
Agency Name
Beverly Hills Unified School District
Contact Types
Lead/Public Agency

Location

Cities
Beverly Hills
Counties
Los Angeles
Cross Streets
Various
Zip
90212/10
State Highways
Hwy 2, I-10

Notice of Determination

Approving Agency
BHUSD
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print