Missouri Flat-Gold Hill 115 kV Power Line Reconductoring Project (A. 13-08-014)

3 Documents in Project

Summary

SCH Number
2014122065
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Missouri Flat-Gold Hill 115 kV Power Line Reconductoring Project (A. 13-08-014)
Document Type
NOD - Notice of Determination
Received
Posted
11/20/2015
Present Land Use
Industrial, Commercial, Residential, Open Space, Public, Multiple El Dorado County and City of Folsom zoning designations
Document Description
PG&E, in its California Public Utilities Commission application (A. 13-08-014) filed on August 13, 2013, requests a Permit to Construct the proposed project, which includes: reconductoring 12.5 miles of Missouri Flat 115 kV power line; replacement of 61 existing tubular steel poles (TSPs) with new TSPs; undergrounding of 1,000 feet of existing 21 kV overhead distribution line; modification of 13 lattice steel towers; reconductoring 7 miles of Gold Hill No. 1 60 kV power line; replacement of 80 existing wood poles with new wood or light-duty steel poles; relocation of 150 feet of existing distribution feeder line; and modification to existing substations and switching stations. All construction would occur in El Dorado County and the City of Folsom, in Sacramento County.

Contact Information

Name
Connie Chen
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Folsom
Counties
El Dorado, Sacramento
Cross Streets
Several
Zip
Multiple
Parcel #
Several
State Highways
Hwy 50
Airports
Cameron Airpark
Schools
Multiple
Waterways
Multiple
Other Location Info
Cameron Park, El Dorado Hills

Notice of Determination

Approving Agency
Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print