PA-1400218 (SA)

3 Documents in Project

Summary

SCH Number
2014122053
Lead Agency
San Joaquin County
Document Title
PA-1400218 (SA)
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2015
Present Land Use
Agricultural / AG-40 / A/G

Document Description
A Site Approval application of ShellPro, Inc (c/o Mike Smith Engineering, Inc. to expand an existing agricultural waste facility for shell grinding in four phases over 10 years. Phase 1 to include the construction of a new 576-square-foot restroom building. Phase 2, with building permits to be issued within 5 years, includes the construction of a new 12,000-square-foot warehouse building. Phase 3, with building permits to be issued within 8 years, includes the construction of a new 12,000-square-foot warehouse building. Phase 4, with building permits to be issued within 10 years, includes the construction of a new 12,000-square-foot warehouse building. This parcel is not under Williamson Act contract. The Property is zoned AG-40 (General Agriculture, 40-acre minimum) and the General Plan designation is A/G (General Agriculture).

Contact Information
Sonia Serrano
San Joaquin County
1810 East Hazelton Avenue
Stockton, CA 95205

Phone : (209) 468-3120

Location

Cities
Lodi
Counties
San Joaquin
Cross Streets
Atkins Road and Brandt Road
Zip
95240
Total Acres
42.36
Parcel #
019-200-15
Waterways
Bear Creek, Paddy Creek

Notice of Determination

Approving Agency
San Joaquin County
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
San Joaquin County, 1810 East Hazelton Avenue, Stockton, CA 95205

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search