Calaveras River Giannecchini C13-D Pump

6 Documents in Project

Summary

SCH Number
2014122043
Lead Agency
Stockton East Water District
Document Title
Calaveras River Giannecchini C13-D Pump
Document Type
NOD - Notice of Determination
Received
Posted
9/16/2016
Present Land Use
PLU: Agricultural Z: AG-40 GPD: A/G
Document Description
This project involves the installation of a removable river pump in the Calaveras River with a capacity of 1,200 gallons per minute (gpm). A previous Neg Dec was adopted on Jan 20, 2015. The project is now revised to include water diversion up to 7,000 gpm. The revised project also includes installation of a 20-inch diameter pipe to support a self cleaning rotor fish screen. The revised project with increased demand would be satisfied by the District's water releases during irrigation seasons. The proposed changes will not result in new significant impacts and an Addendum is appropriate under CEQA Guidelines Section 15164.

Contact Information

Name
Scot A. Moody
Agency Name
Stockton East Water District
Contact Types
Lead/Public Agency

Location

Counties
San Joaquin
Cross Streets
Highway 26
Zip
95236
Total Acres
.23
Parcel #
067-250-02
State Highways
Hwy 26
Railways
No
Airports
No
Schools
No
Waterways
Calaveras River, Mormon Slough, Duck Creek
Township
3N
Range
9E
Section
34
Other Location Info
Bellota

Notice of Determination

Approving Agency
Stockton East Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print