California Department of Forestry and Fire Protection (CAL FIRE)
Document Title
Butte Fire Station and Unit Headquarters Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
2/18/2015
Present Land Use
GPLUD: Public/Quasi-Public Z: Public or Quasi-Public
Document Description
Demolition of Existing Butte Fire Station and Unit Headquarters Site demolition would include all buildings on-site except for the two Emergency Command Center (ECC) buildings and the ECC tower located in the northeast corner of the Project site. In addition to building demolition, the existing hose rack, fuel tanks and propane tanks, all existing utilities and appurtenances including water distribution lines, sewer lines, and gas lines, and existing concrete retaining walls, asphalt concrete paving and concrete sidewalks would be removed. A utility pole located on the eastern boundary would also be relocated. Lastly, clearing, grubbing, and tree removal would occur as required within the limits of the Project site. New Butte Fire Station and Unit Headquarters After demolition, a new fire station and unit administrative headquarters complex would be constructed. New facilities would include: administrative building, three-bay fire apparatus building, 20-bed barracks/mess hall, warehouse/service center, two-bay dozer shed, auto shop, covered vehicle wash rack with filtration system, maintenance support building, physical fitness building, a generator/storage building, a fire pump test pit and several other site improvements.

Contact Information

Name
Stephanie Coleman
Agency Name
Cal Fire
Contact Types
Lead/Public Agency

Location

Cities
Oroville
Counties
Butte
Cross Streets
176 Nelson Avenue
Zip
95221
Total Acres
4.36
Parcel #
031-040-015-000
State Highways
SR 70
Schools
Oroville Community Day
Waterways
Feather River
Township
16N
Range
4E
Section
7
Base
MDB&M

Notice of Determination

Approving Agency
Cal Fire
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.