Pitt Street Bridge Replacement Project (Streambed Alteration Agreement No. 1600-2016-0007-R2)

2 Documents in Project

Summary

SCH Number
2014122012
Lead Agency
City of Jackson
Document Title
Pitt Street Bridge Replacement Project (Streambed Alteration Agreement No. 1600-2016-0007-R2)
Document Type
NOD - Notice of Determination
Received
Posted
4/13/2016
Present Land Use
Right-of-way
Document Description
CDFW has executed Streambed Alteration Agreement No. 1600-2016-0007-R2, pursuant to section 1602 of the Fish and Game Code to the Project applicant, City of Jackson (the Permittee) as represented by Michael Daly. The project includes demolition and replacement of the Pitt Street Bridge. The replacement bridge will be of a similar profile, single-span bridge, 54 feet-long by 32-feet wide. The project would conform to the existing roadway elevation on the northwest end and the southeast end vertical elevation would be slightly revised. The new abutments would likely be founded on spread footings or doweled directly into native bedrock. With the installation work on the new abutments and footings, the creek channel would be recontoured between the new abutments.

Contact Information

Name
Kursten Sheridan
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Jackson
Counties
Amador
Cross Streets
Water Street and Pitt Street
Zip
95642
Total Acres
.397
State Highways
Hwy 88
Schools
Jackson ES
Waterways
Middle Fork Jackson Creek
Township
6N
Range
11E
Section
21

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.