Water Pollution Control Facility Solar Power Project

3 Documents in Project

Summary

SCH Number
2014112048
Lead Agency
City of Woodland
Document Title
Water Pollution Control Facility Solar Power Project
Document Type
NOD - Notice of Determination
Received
Posted
1/8/2015
Present Land Use
The location of one of the solar power facilities would be on fallow land that was previously a deposition site for tomato processing waste material and more recently a deposition site for excess soil from regional construction projects, northeast of the treatment facilities, consisting of ~0.2 acres. The project site's current City of Woodland zoning designation is Open Space (O-S) and the current City of Woodland General Plan land use designation is Urban Reserve (UR) and Public Service (PS).
Document Description
Installation and operation of solar photovoltaic systems at two locations at and adjacent to the City's Water Pollution Control Facility (WPCF). One array would be at a screw pump on the WPCF premises and the other would be on 7 acres of fallow land NE of the facility. The 1.5-megawatt (MW) systems would generate about 2.4 MW-hours annually.

Contact Information

Name
Roberta Childers
Agency Name
City of Woodland
Contact Types
Lead/Public Agency

Location

Cities
Woodland
Counties
Yolo
Cross Streets
County Road 103 and County Road 24
Zip
95776
Total Acres
7.2
Parcel #
042-580-034-000 and 027-390-022-000
State Highways
I-5, SR 16
Schools
Woodland Comm. College, Ramon Tafoya ES, Pioneer HS
Waterways
Willow Slough
Township
10N
Range
2E
Section
36
Base
MDB&M

Notice of Determination

Approving Agency
City of Woodland
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print