Sunnyvale Water Pollution Control Plant Primary Treatment Faciity (Project); Clean Water State Revolving Fund (CWSRF_ No. C-06-8153-110

6 Documents in Project

Summary

SCH Number
2014112037
Lead Agency
City of Sunnyvale
Document Title
Sunnyvale Water Pollution Control Plant Primary Treatment Faciity (Project); Clean Water State Revolving Fund (CWSRF_ No. C-06-8153-110
Document Type
NOD - Notice of Determination
Received
Posted
3/9/2017
Present Land Use
Environmental Services
Document Description
The proposed project would replace existing, aging facilities at the WPCP, including replacements of the headworks facility, primary treatment facilities, switchgear building, standby generator, and heat recovery system at the power generation facility. Access roadways and fencing would also be altered or replaced, a stormwater channel along the southeast boundary of the WPCP site would be filled, and dewatering would be relocated within the WPCP site. These alterations will occur within the main plant as well as in surrounding areas of the WPCP. For the oxidation ponds, the proposed Project may include, but is not limited to, construction of a new road by expanding the existing levees between Pond 1 and 2 on the west side of Moffett Channel, replacement of existing pipelines, and extension of the primary effluent pipeline to new equalization basin.

Contact Information

Name
Amanda Dwyer
Agency Name
SWRCB
Contact Types
Lead/Public Agency

Location

Cities
Sunnyvale
Counties
Santa Clara
Cross Streets
Carl Road and Borregas Avenue
Zip
94089
Total Acres
16.6
Parcel #
110-03-023, 110-03-064
State Highways
Hwy 237, 101
Railways
Santa Clara Light Rail
Airports
Moffett Airfield

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.