Vineyard Elementary School Annex

2 Documents in Project

Summary

SCH Number
2014111023
Lead Agency
Templeton Unified School District
Document Title
Vineyard Elementary School Annex
Document Type
NOD - Notice of Determination
Received
Posted
1/12/2015
Present Land Use
Public Facility
Document Description
The Proposed Project consists of a new 2nd and 3rd grade elementary school as an annex to the existing Vineyard Elementary School adjacent to the west. The initial enrollment capacity will be approximately 450 students. The project will be designed to eventually accommodate 600 students. Site work will include earthwork over the 12.4 acre site, parking and internal access roads, sports fields and play area, hardcourt for games, site lighting and entry sign. Off-site work includes striping of Vineyard drive to accommodate turn lanes into and out of the project. A sewer line will be extended to Malvasia Court to connect to the Templeton community Services District sewer main. The project will shaft around the current elementary student population within the District. In the 2016-2017 school year enrollment is forecast to decrease at Templeton Elementary School by about 177 and at Vineyard Elementary School by 165. These students plus forecast increases will result in 378 students enrolled at the proposed Vineyard Elementary School Annex in 2016-2017.

Contact Information

Name
Chris Bonin
Agency Name
Templeton Unified School District
Contact Types
Lead/Public Agency

Location

Counties
San Luis Obispo
Cross Streets
Vineyard Drive and Malvasi Curt
Zip
93465
Total Acres
12.4
Parcel #
039-223-053
Other Location Info
Templeton

Notice of Determination

Approving Agency
Templeton Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print