Harbor-UCLA Replacement Program - Construction Change Orders
7 Documents in Project
Summary
SCH Number
2014111004
Lead Agency
Los Angeles County Department of Public Works
(DPW)
Document Title
Harbor-UCLA Replacement Program - Construction Change Orders
Document Type
NOD - Notice of Determination
Received
Posted
11/19/2024
Document Description
On October 22, 2024, the Board approved four change orders for the Harbor-UCLA Medical Center Replacement Project. The approved change orders include the double-ended electrical substation for distribution of 480-volt power in a redundant fashion at the Outpatient/Support Building; a redundant source of electrical power to Intermediate Distribution Frame Rooms at the Outpatient/Support Building; removal and disposal of contaminated soil encountered during excavation for the Inpatient Tower; and the Campus Network Integrator services and infrastructure for the program wide Building Automation System. Work is in accordance with the environmental Impact Report (EIR) Addendum certified by the Board of Supervisors on February 8, 2022 for the Harbor-UCLA Medical Center Replacement Project. The original EIR was certified on December 20, 2016.
Contact Information
Name
Gillian Tiede
Agency Name
Los Angeles County Public Works
Job Title
Capital Projects Program Manager
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project
Phone
Email
Location
Cities
Torrance
Counties
Los Angeles
Regions
Southern California
Cross Streets
W Carson St and S Vermont Ave
Zip
90502
Parcel #
7344-001-901
Other Location Info
1000 W. Carson Street, Torrance, CA 90502
Notice of Determination
Approving Agency
Los Angeles County
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
https://pw.lacounty.gov/harbor-ucla-rp/documents
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.