McKean Road Tank and Pipeline Project

3 Documents in Project

Summary

SCH Number
2014102023
Lead Agency
City of San Jose
Document Title
McKean Road Tank and Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
7/25/2016
Present Land Use
Open Hillside; R-1-1, RR-h1 / RR-d1-sr / RR-d1-sr-h1, A-20Ac-d1-sr, HS/HS-d1-sr / HS-sr / HS-sr-h1 (San Jose and Santa Clara County)
Document Description
The project is part of a larger project which includes installing 3300 feet of water pipeline and a storage tank to improve operational storage in service area for San Jose Water Company. The project covered under the Lake and Streambed Alteration Agreement No. 1600-2015-0176-R3 CDFW is executing pursuant to Section 1602 of the Fish and Game Code, is limited to the construction of a 150-foot long by 4-foot wide prefabricated bridge across Alamitos Creek, tributary to Guadalupe River, just east of Almaden Road, City of San Jose, and a 50-foot long by 10--foot wide pipe/vehicle bridge across the Almaden-Calero Canal. Concrete abutments for the Alamitos Creek bridge will be installed on each side of the creek outside of the floodplain and riparian wetlands adjacent to the creek. The bridge will be built off site and installed using a crane once the abutments are in place. The pipeline will be installed via open-cut trenching within existing swales. The open-cut method will require a workable trench of 3 to 5 feet wide and excavation to a depth of 6 to 15 feet. The disturbed area along the pipeline alignment will be restored to pre-disturbance conditions by backfilling the trench, leveling to match the surrounding grade, and seeding with an appropriate native grass mixture.

Contact Information

Name
Suzanne DeLeon
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
Between Almaden Road and McKean Road
Total Acres
6.7
Parcel #
724-09-048, 49, 13, 47, 50, 24, 15
Waterways
Alamitos Creek, Almaden-Calero canal
Township
8S
Range
1E
Base
MDB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.