North Haiwee Dam No. 2 Project

9 Documents in Project

Summary

SCH Number
2014101065
Lead Agency
City of Los Angeles
Document Title
North Haiwee Dam No. 2 Project
Document Type
NOD - Notice of Determination
Received
Posted
7/27/2018
Present Land Use
Multiple land uses: natural resources, local and federal lands - undeveloped LADWP-owned and BLM-Managed lands)
Document Description
The Project is to improve the seismic reliability of the North Haiwee Reservoir through construction of a new dam, North Haiwee Dam No. 2 (NHD2), in order to maintain the function of an essential water conveyance infrastructure for the City of LA, as well as to protect local populations from a hazardous flooding event. The Project consists of the following 4 components: 1) Construction of the NHD2; 2) Realignment of Cactus Flats Road; 3) Realignment of the LA Aqueduct, which includes excavation of various materials and construction of the diversion structure and temporary bridge; and 4) Construction of the diversion channel and North Haiwee Dam modifications.

Contact Information

Name
Brian Gonzales
Agency Name
City of Los Angeles
Contact Types
Lead/Public Agency

Location

Counties
Inyo
State Highways
395
Waterways
Los Angeles Aqueduct, North Haiwee Reservoir, various
Other Location Info
Olancha, Haiwee, Lone Pine, Keeler

Notice of Determination

Approving Agency
LA Dept. of Water and Power
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print