The Vineyards at Sand Creek Outfall Structure Project (Lake or Streambed Alteration Agreement No. 1600-2016-0136-R3)
6 Documents in Project
Summary
SCH Number
2014092010
Lead Agency
City of Antioch
Document Title
The Vineyards at Sand Creek Outfall Structure Project (Lake or Streambed Alteration Agreement No. 1600-2016-0136-R3)
Document Type
NOD - Notice of Determination
Received
Posted
1/23/2017
Present Land Use
Various
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0136-R3, pursuant to section 1602 of the Fish and Game Code to the Project applicant, GBN Partners, LLC as represented by Mr. Earl Callison.
The project is associated with the development of the Vineyards at Sand Creek residential Project. The Project is limited to the construction of a single storm drain outfall structure that will discharge water into Sand Creek from a water quality control basin. The outfall structure will consist of a 60-inch drain pipe with 1,200 sq. ft. of rip-rap (180 cubic yards) used to construct the outfall. Approx. 40 linear feet of the pipe will occur in the historical riparian upland and the rip-rap apron will occur in the historical riparian upland area below the top of bank and will permanently impact an area approx. 1,200 sq. ft. for outfall construction within the riparian upland below top of bank. No trees shall be removed as a result of Project implementation.
Contact Information
Name
Melissa Farinha
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Antioch
Counties
Contra Costa
Cross Streets
Old Sand Creek Road / Heidorn Ranch Road
Zip
94531
Total Acres
141
Parcel #
057-030-003, -004, 057-050-007
State Highways
Hwy 4
Schools
Various
Waterways
Sand Creek
Township
1N
Range
2E
Section
9
Base
MDB&M
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No