PG&E Gas Transmission Line 123 Pipeline Replacement Project, Phase 2 Sections 2B2, 1C, 2C1, and 2C2

3 Documents in Project

Summary

SCH Number
2014092007
Lead Agency
Regional Water Quality Control Board, Region 5 (Central Valley), Sacramento
Document Title
PG&E Gas Transmission Line 123 Pipeline Replacement Project, Phase 2 Sections 2B2, 1C, 2C1, and 2C2
Document Type
FIN - Final Document
Received

Document Description
Note: Final 1 Copy PG&E proposes to replace four sections of gas transmission line 123 (L-123): Sections 2B2, 1C, 2C1, and 2C2. The project would replace 0.85 mile of existing 12-inch-diameter underground natural gas transmission pipeline with 0.91 mile of 16-inch-diameter underground natural gas transmission pipeline.

Contact Information
Trevor Cleak
Regional Water Quality Control Board, Region 5 (Central Valley),
11020 Sun Center Drive, Suite 200
Rancho Cordova, CA 95670

916 464 4684

Location

Coordinates
38°51'38.72"N 121°19'.78"W
Cities
Lincoln
Counties
Placer
Cross Streets
Langton Ct/Forebridge Ln (2C2, Athens Ave/Thunder Valley Court (2C1, 1C, and 2B2)
Zip
95648
Total Acres
11.21
Parcel #
021-283-010, 021-283-026, 021-282
State Highways
Hwy 65
Railways
UPRR
Schools
Lincoln Crossing Element
Waterways
Orchard Creek, scattered wetland complexes
Township
11N
Range
6E
Section
4/9

Notice of Completion

Development Type
Other (Pipeline Replacement)
Project Issues
Cumulative Effects Landuse Wetland/Riparian Water Supply Water Quality Vegetation Traffic/Circulation Toxic/Hazardous Solid Waste Soil Erosion/Compaction/Grading Recreation/Parks Public Services Population/Housing Balance Noise Minerals Geologic/Seismic Forest Land/Fire Hazard Flood Plain/Flooding Drainage/Absorption Biological Resources Archaeologic-Historic Air Quality Agricultural Land