Phillips 66 5.6 Mile Pipeline; Minor Use Permit; DRC2012-00101

3 Documents in Project

Summary

SCH Number
2014091070
Lead Agency
San Luis Obispo County
Document Title
Phillips 66 5.6 Mile Pipeline; Minor Use Permit; DRC2012-00101
Document Type
NOD - Notice of Determination
Received
Posted
12/1/2014
Present Land Use
Various, Roadway Right of Way
Document Description
Request by Phillips 66 Pipeline LLC for a Minor Use Permit to construct; operate; and, maintain a 3.9 mile segment of a proposed 5.6 mile oil pipeline and appurtenant facilities within County of San Luis Obispo. The remaining 1.7 miles of the proposed pipeline and appurtenant facilities would be located within the cities of Pismo Beach (0.8 miles), Grover Beach (0.5 miles) and Arroyo Grande (0.4 miles) and would require approval separate approval by the respective city. The hearing will also consider adoption of the Mitigated Negative Declaration prepared for the project, which analyzed the entirety of the project and is available online at: http://www.slocounty.ca.gov/planning/environmental/EnvironmentalNotices.htm. The proposed pipeline alignment would be located within/under existing roadway right-of-way. The project would transport crude oil from the existing Freeport McMoran Oil Field (Price Canyon/Arroyo Grande Oil Field) located at 1821 Price Canyon Road to its existing 12-inch pipeline located at the intersection of Oak Park Drive and Grande Avenue in the City of Arroyo Grande. The existing 12-inch pipeline located connects to the existing Santa Maria oil refinery at 2555 Willow Road on the Nipomo Mesa. The project also includes installation of above ground facilities at the existing Summit Station facility located at 1364 Dale Avenue, south of Arroyo Grande. In addition, the project would replace an existing P66 pipeline with Arroyo Grande Check.

Contact Information

Name
Rob Fitzroy
Agency Name
San Luis Obispo County
Contact Types
Lead/Public Agency

Location

Cities
Pismo Beach
Counties
San Luis Obispo
Cross Streets
Various, Linear Project
Zip
93447
Total Acres
5.93
Parcel #
Various, Roadway Right of Way
State Highways
Hwy 101
Airports
San Luis Obispo
Schools
Lucia Mar USD
Waterways
Pismo Creek, Arroyo Grande Creek

Notice of Determination

Approving Agency
San Luis Obispo County Planning Department Hearing
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print