Big Tree Creek Stormwater Compliance Project (Lake or Streambed Alteration Agreement No. 1600-2015-0218-R2)

4 Documents in Project

Summary

SCH Number
2014081040
Lead Agency
California Department of Transportation, District 6
Document Title
Big Tree Creek Stormwater Compliance Project (Lake or Streambed Alteration Agreement No. 1600-2015-0218-R2)
Document Type
NOD - Notice of Determination
Received
Posted
4/14/2016
Present Land Use
State Highway
Document Description
The project will widen the existing roadway on both sides to provide 8-foot paved shoulders, a 10-foot paved gutter on the left side of the hwy and a 3-foot paved gutter on the right side of the hwy to accommodate storage area for snow removal. The scope of work includes construction of approx. 800 linear feet of retaining walls and 2,400 linear feet of concrete barrier located on he south side of the hwy within the riparian area of Big Tree Creek. Temporary reinforced silt fence along the entire length of the project to assure will be installed to avoid additional impacts to the Creek. The new embankment will be keyed into the existing slope and compacted in layers to ensure stability. The existing pavement will be overlaid with asphalt concrete. Existing drainage facilities will be modified along with the addition of new drainage facilities. The drainage facilities will be constructed as traction sand traps. The traction sand traps will temporarily detain runoff and allow traction sand that was previously applied to snowy or icy roads to settle out. These traction sand traps are the storm water management plan approved permanent treatment best management plans for statewide application to address sand which is the non-storm water discharge of concern. Overhead power and underground telephone facilities will require relocation. There are also sewer facilities in the area but relocation is not anticipated. The project will upgrade the existing 18-inch diameter corrugated steel pipe (CSP) or concrete. The existing drainage inlets located in the existing drainage ditch that parallels the hwy on the north side will be removed and replaced with sand trap type drainage inlets in the new ditch line.

Contact Information

Name
Juan Lopez Torres
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Counties
Calaveras
Cross Streets
SR 4, .2 miles outside main entrance of Calaveras Big Trees State Park
Total Acres
2.9
State Highways
Hwy 4
Waterways
Big Tree Creek
Other Location Info
Arnold

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.