Los Angeles Regional Interoperable Communications System (LA-RICS) Land Mobile Radio (LMR) Project
29 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2014081025
- Lead Agency
- United States Air Force (USAF)
- Document Title
- Los Angeles Regional Interoperable Communications System (LA-RICS) Land Mobile Radio (LMR) Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 9/14/2018
- Present Land Use
- Department of Defense military installation
- Document Description
- Site Access Agreement at Site LACF072 allows for implementation of the LMR System, which consists of installation of antennas on a new 70-foot tall monopole and supporting radio equipment in a new shelter for Site LACF072. The environmental impacts of prject implementation at this site were evaluated in an Environmental Impact report certified by the LA-RICS JPA Board on March 29, 2016. There have been no changes to the project or to the circumstances under which the project is undertaken since that approval that would require new analysis or mitigation under CEQA.
- Contact Information
-
Susy Orellana-Curtis
LA-RICS Joint Powers Authority
Lead/Public Agency
2525 Corporate Place, #100
Monterey Park, CA 91754
Phone : (323) 881-8292
Location
- Coordinates
- 34°35'55.9"N 120°38'10.1"W
- Cities
- Lompoc
- Counties
- Santa Barbara
- Zip
- 93436
- Total Acres
- 13.2
- State Highways
- No
- Railways
- UPRR
- Airports
- No
- Waterways
- Honda Creek
- Other Information
- Site LACF072
Notice of Determination
- Approving Agency
- LA-RICS Joint Powers Authority
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 2525 Corporate Place, Suite 100, Monterey Park, CA 91754
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- Yes
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.