Delta Coves Utility Project, Addendum #1 to MND

4 Documents in Project

Summary

SCH Number
2014072026
Lead Agency
Diablo Water District
Document Title
Delta Coves Utility Project, Addendum #1 to MND
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2015
Present Land Use
No changes
Document Description
The main objective of the Delta Coves Utility Project, as analyzed by the MND, is to serve the future residents of Delta Coves with potable water for domestic and fire suppression purposes and natural gas from the PG&E gas pipeline. A MND was previously prepared for the Delta Coves Utility Project, and adopted on August 27, 2004 by the Board of Directors of the Diablo Water District (DWD). An Addendum to the MND has been prepared for the purpose of addressing minor changes to the original project design, which consist of refined plans for the two antenna towers located at the Chloramination Plant, and the Pump Station Site. These two antennae structures were previously identified as being "approximately 40 to 50 ft high." The necessary project design specifications have shown that these antennae structures will each be approximately 90 ft high with one containing a 3" diameter antenna extending 10 ft above the top of the structure. Pursuant to CEQA guidelines, since the revised plans do not lead directly or indirectly to significant physical changes in the project, nor do these refined plans alter the adequacy or the completeness of the environmental impacts and mitigation measures identified in the MND; no public review was necessary.

Contact Information

Name
Mike Yeraka
Agency Name
Diablo Water District
Contact Types
Lead/Public Agency

Location

Cities
Oakley
Counties
Contra Costa
Cross Streets
Bethal Island Road / East Cypress Road / Sandy Land
Zip
94561
Railways
Amtrack
Schools
Delta Valley MS
Waterways
Dutch Slough
Township
2-4N
Range
3E
Section
Multi
Other Location Info
Bethal Island

Notice of Determination

Approving Agency
Diablo Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print