Davis Family Estates Friesen Vineyard Project - Timberland Conversion # 611

4 Documents in Project

Summary

SCH Number
2014062076
Lead Agency
Forestry and Fire Protection, Department of (Cal Fire)
Document Title
Davis Family Estates Friesen Vineyard Project - Timberland Conversion # 611
Document Type
NOD - Notice of Determination
Received
Posted
8/1/2018
Present Land Use
Agricultural Watershed (AW)

Document Description
Conversion of 14 acres of timberland to a commercial vineyard. A Timberland Conversion Permit (TCP) and Napa County Erosion Control Plan (ECP) are required for the Project Site. A Timber Harvest Plan (THP) is being prepared concurrently for the harvest of 10 acres within the Project Site (the balance of 4 acres within the Project Site is comprised of grass, brush, and ruderal land). Vineyard blocks will include wine grape vines and internal farm avenues and space for vineyards maintenance operations; the net area of the vineyard will be approximately 10.5 acres. Groundwater will be used for irrigation. Post-project sediment erosion conditions and peak hydrological runoff are projected to be below pre-project conditions.

Contact Information
Bill Solinsky
Cal Fire
P.O. Box 944246
Sacramento, CA 94244-2460

Phone : (916) 657-0300

Location

Coordinates
38°36'14.3"N 122°29'.81"W
Counties
Napa
Cross Streets
Friesen Drive
Zip
94508
Total Acres
38.7
Parcel #
018-060-012, 018-060-013
Waterways
Wild Lake, unnamed reservoir
Township
9N
Range
6W
Section
25
Base
MDB&M
Other Location Info
Angwin

Notice of Determination

Approving Agency
Calfire
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
1416 Ninth St., 15th Floor, Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search