Hayford Flume #2 Replacement Project
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2014062003
- Lead Agency
- Placer County Water Agency
- Document Title
- Hayford Flume #2 Replacement Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/18/2014
- Present Land Use
- F-B 100 (Farm-Building, 100,000 sf minimum) / Ranchette, 2.5- to 20-acre minimum
- Document Description
- The proposed project involves replacing the existing, elevated Hayford Flume #2 on the Boardman Canal system. The existing 175-foot-long flume would be removed and a new 435-foot-long conveyance pipeline system installed to provide a conveyance for the Boardman Canal flows. The proposed project also includes construction of a new 175-foot-long access road to facilitate access to the work area and provide better access for future maintenance activities. The pipeline will be installed in an engineered bench to traverse the nearby hillside. Hayford Flume #2 would be demolished and removed after the new conveyance system is operational.
- Contact Information
-
Heather Trejo
Placer County Water Agency
PO Box 6570
Auburn, CA 95604
Phone : (530) 823-4886
Location
- Coordinates
- 39°6'9.6"N 120°9.7'15"W
- Cities
- Colfax
- Counties
- Placer
- Cross Streets
- Placer Hills Road
- Total Acres
- 1
- Parcel #
- 071-111-067 and 071-111-057
- State Highways
- Hwy 80
- Railways
- UPRR
- Airports
- No
- Schools
- No
- Waterways
- Bear River
- Township
- 14N
- Range
- 9E
- Section
- 16
Notice of Determination
- Approving Agency
- Placer County Water Agency
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- Placer County Water Agency's Business Center at 144 Ferguson Road in Auburn, California 95603
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.