Addendum to the Water Supply and Distribution Improvement Project Mitigated Negative Declaration

4 Documents in Project

Summary

SCH Number
2014061024
Lead Agency
Pixley Public Utility District
Document Title
Addendum to the Water Supply and Distribution Improvement Project Mitigated Negative Declaration
Document Type
NOD - Notice of Determination
Received
Posted
7/9/2024
Document Description
The Project would amend the adopted MND by the addition of a new well (Well 4A) instead of the Well 2A modification and the Well 4 abandonment. Well 2A was not able to be modified and has been abandoned. Well 4 is no longer being abandoned but will remain online. Because Well 4 is not reliable, a new well (Well 4A) will be constructed on the existing Well 4 site. The two wells would utilize a bypass switch and would not operate at the same time. These changes do not expand capacity of the water system beyond what was discussed in the 2014 IS/MND. The adopted CEQA document did not include Well 4A. No additional changes or equipment would be needed with the Project as the original equipment required in the MND would be adequate to meet the needs of the Project. Construction time is not anticipated to change from what was approved in the MND.

Contact Information

Name
Ronnie Prine
Agency Name
Pixley Public Utility District
Job Title
Board President
Contact Types
Lead/Public Agency

Location

Cities
Community of Pixley
Counties
Tulare
Regions
Southern California
Parcel #
299-150-034
Other Location Info
Community of Pixley, Tulare County

Notice of Determination

Approving Agency
Pixley Public Utility District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Tulare
Final Environmental Document Available at
Pixley Public Utility District, 232 East Davis Avenue, Pixley, CA 93256

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print