Temecula Old Town Sewer Improvements Project
3 Documents in Project
Summary
SCH Number
2014051043
Lead Agency
Eastern Municipal Water District
(EMWD)
Document Title
Temecula Old Town Sewer Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
7/22/2014
Present Land Use
Public Institutional Facilities
Document Description
The Eastern Municipal Water District's proposes to construct and operate a relief sewer located along Front Street in Old Town Temecula, Riverside County. The purpose of the project is to provide added sewer capacity to support growth within the Old Town Temecula area. The project would use a tunneling method to install the new sewer under the sidewalk along the south side of Front Street.
The new sewer includes the installation of approximately 3,100 linear feet of 15-inch diameter pipeline in parallel with an existing 8-inch diameter sewer pipeline. Vertical shafts up to 12-feet in diameter would be constructed at street intersections to facilitate the tunneling work under the sidewalk. Drop manholes would be installed along with interconnections between the existing and new sewer, at the intersections of Front Street at Moreno Drive, Second, Third, Fourth and Sixth Streets. The interconnections between the new and existing sewer would use eight-inch diameter pipes. Access manholes would also be installed at the intersections of Front Street at Fifth, Main and First Streets.
Contact Information
Name
Helen Stratton
Agency Name
Eastern Municipal Water District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Temecula
Counties
Riverside
Cross Streets
Front Street and Moreno Road southeast to Front Street and First Street
State Highways
I-15
Township
8S
Range
3W
Section
12
Notice of Determination
Approving Agency
Eastern Municipal Water District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.