Dubbink Family Trust Minor Use Permit/ Coastal Development Permit; and Lot Line Adjustment; DRC2011-00100 /SUB 2011-00054/ COAL 12-0038

2 Documents in Project

Summary

SCH Number
2014041084
Lead Agency
San Luis Obispo County
Document Title
Dubbink Family Trust Minor Use Permit/ Coastal Development Permit; and Lot Line Adjustment; DRC2011-00100 /SUB 2011-00054/ COAL 12-0038
Document Type
NOD - Notice of Determination
Received
Posted
6/19/2014
Present Land Use
Residential SIngle Family, Local Coastal Program, Archaeological Study Area, and Sensitive Resource

Document Description
Request by the Dubbink Family Trust for a Minor Use Permit / Coastal Development Permit and Lot Line Adjustment to: allow for a 2,336 square foot addition to an existing single family residence (a studio/gallery of 946 square feet, an office/bedroom of 595 square feet, a 93 square foot addition to the living room, a garage of 306 square feet, and a 396 square foot deck), and adjust the lot lines between two parcels of 27,138 square feet and 23,216 square feet each. The adjustment will result in two parcels of 35,414 square feet and 14,940 square feet each. The project will not result in the creation of any additional parcels. The project will result in a disturbance of 4,000 square feet.

Contact Information
Kerry Brown
San Luis Obispo County
976 Osos Street, Rm 200
San Luis Obispo, CA 93408-2040

Phone : (805) 781-5600

Location

Coordinates
35°19'51.492"N 120°50'.312"W
Counties
San Luis Obispo
Cross Streets
9th and Santa Ysabel
Other Location Info
Los Osos

Notice of Determination

Approving Agency
San Luis Obispo County Subdivision Review Board
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
976 Osos Street Rm 200 San Luis Obispo, Ca 93408

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes