Peachtree Road Bridge Replacement Project (California Endangered Species Act Incidental Take Permit No. 2081-2014-041-04 (ITP))
4 Documents in Project
Summary
SCH Number
2014041065
Lead Agency
Monterey County
Document Title
Peachtree Road Bridge Replacement Project (California Endangered Species Act Incidental Take Permit No. 2081-2014-041-04 (ITP))
Document Type
NOD - Notice of Determination
Received
Posted
1/6/2015
Present Land Use
rural roadway
Document Description
The Project includes the replacement of the existing Peachtree Road Bridge over Pancho Rico Creek with a structure that will meet current Caltrans seismic codes. The new bridge will be approx. 28 ft. wide and 80 ft. long and will clear-span Pancho Rico Creek. The bridge will be supported by two abutments, one on each side of the creek, outside of the creek channel. Each abutment will have short wing walls and will be supported on 24-inch diameter cast-in-drilled-hole concrete pilings. Rock slop protection with a slope of 1:1 will be provided at each abutment to protect against bank scour, new roadway approaches will be constructed by widening Peachtree Road on both sides of the bridge, and recast/prestressed deck units will be installed.
Contact Information
Name
Brandon Sanderson
Agency Name
CA. Dept. of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Monterey
Cross Streets
Peach Tree Road
Total Acres
1
Waterways
Pancho Rico Creek
Township
21S
Range
12E
Section
22
Other Location Info
San Ardo
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No