The Rivers Erosion Site Project
8 Documents in Project
Summary
SCH Number
2014032085
Lead Agency
West Sacramento Area Flood Control Agency
Document Title
The Rivers Erosion Site Project
Document Type
NOD - Notice of Determination
Received
Posted
8/11/2014
Present Land Use
Public Open Space
Document Description
The proposed project consists of repairing an erosion site through the installation of a ScourStop TM channel, placing vegetated mechanically stabilized earth (VMSE), and constructing a longitudinal stone toe. Placement of the VMSE would restore the slope of the bank, as well as help retain soil placed as part of the project. The longitudinal stone toe would retard erosion from fluvial forces, boat wake, and discharged flows for the ScourStop channel. These repairs would address the existing erosion problems, enhance fish habitat values, and prevent future erosion from encroaching on the levee, the levee maintenance road, the adjacent recreation features.
Contact Information
Name
David Martasian
Agency Name
Department of Water Resources
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
West Sacramento
Counties
Yolo
Cross Streets
Riverbank Road and Todhunter Avenue
Zip
95691
Parcel #
014-580-010
State Highways
I-80, SR 84, US-50
Railways
UPRR
Airports
No
Schools
Bryte, Riverbank ES
Waterways
Sacramento River, American RIver, Sacramento Bypass
Township
9N
Range
4E
Section
28
Notice of Determination
Approving Agency
California Department of Water Resources
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.