Water Right Issuance for North Perris Water System Pipeline

5 Documents in Project

Summary

SCH Number
2014031076
Lead Agency
City of Perris
Document Title
Water Right Issuance for North Perris Water System Pipeline
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2018
Present Land Use
various
Document Description
North Perris Water System Pipeline Project - Proposal for: 1) Water Extraction: An application (Application 31799) for a water appropriation permit to the State Water Resources Control Board to extract up to an additional 863 acre-feet per year from four existing wells servicing the North Perris Water System; 2) Water Pipeline: Installation of approximately 4.6 miles of new underground pipeline to connect existing NPWS facilities with existing City facilities in the Downtown Water System ; and 3) Water Mixing: Mixing of water from two different sources: NPWS (formerly named McCanna Ranch Water Company) water and Downtown Water System water.

Contact Information

Name
Mitchell Moody
Agency Name
SWRCB, Division of Water Rights
Contact Types
Lead/Public Agency

Location

Cities
Perris
Counties
Riverside
Cross Streets
Five mile pipeline, extending from Bradely Rd/Avalon Prkwy to Perris Blvd/Nuevo Rd
State Highways
I-215; SR 74
Waterways
Lake Perris
Township
4
Range
3
Section
21
Base
SBB&M

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.