Mitigated Negative Declaration for the Pipelines 3, 4 and 5 Relining

2 Documents in Project

Summary

SCH Number
2014031074
Lead Agency
San Diego County Water Authority
Document Title
Mitigated Negative Declaration for the Pipelines 3, 4 and 5 Relining
Document Type
NOD - Notice of Determination
Received

Document Description
The proposed project consists of the installation of welded steel liners in portions of P3, P4, and P5. The P3 relining is proposed for a length of approximately 475 feet, while the project proposes relining longer lengths of P4 and P5, at approximately 3,400 feet each. The relining would be performed underground, within the existing pipelines, but worker and equipment access to the interior of the pipelines requires excavation to establish access portals that are grouped at two locations along the alignment. Other above-ground activities would include worker and equipment access at existing manhole stations and blow-off valve stations along the project alignment, equipment storage, and activity at specified staging areas.

Contact Information
Mark Tegio
San Diego County Water Authority
1600 Pacific Highway, Rm. 260 MS A-33
San Diego, CA 92101

858 522 6753

Location

Cities
Fallbrook
Counties
San Diego
Cross Streets
SR 76, Dulin Road, Sage Road, Brodea Lane, Mountain View Road
Zip
Various
Total Acres
16.5
Parcel #
Various
State Highways
SR 76, I-15
Railways
No
Airports
No
Schools
Sullivan MS
Waterways
San Luis Rey River
Township
17/18S
Range
1W/1E
Section
Varies
Base
SBB&M
Other Location Info
Bonsall

Notice of Determination

Approving Agency
San Diego County Water Authority
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
San Diego County Water Authority Administration Building, 4677 Overland Avenue, San Diego, CA 92123.

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search