Alta Loma High School Improvement Project

3 Documents in Project

Summary

SCH Number
2014031019
Lead Agency
Chaffey Joint Union High School District (CJUHSD)
Document Title
Alta Loma High School Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
10/13/2014
Present Land Use
GPD: High School Z: Low Residential (2-4 DU/AC) (L)
Document Description
The District proposes to perform improvement to the Campus including the construction of new athletic facilities, and the renovation of existing athletic facilities on the 40-acre property. The improvements would include the construction of a new stadium complex, upgrades to the existing aquatic center, and reconfiguration of the baseball, softball, and soccer fields. The District anticipates that construction would last approximately 16 months with construction starting in November 2014, and ending March 2016, based on the required approval from the Department of the State Architect.

Contact Information

Name
Mike Harrison
Agency Name
Chaffey Joint Union High School District
Contact Types
Lead/Public Agency

Location

Cities
Rancho Cucamonga
Counties
San Bernardino
Cross Streets
Base Line Rd at Vineyard Ave
Zip
91701
Total Acres
40
Parcel #
0202-032-33-0000
State Highways
SR-210
Railways
AT&SF
Airports
No
Schools
Carnelian ES, Valle Vista
Waterways
Cucamonga Creek Channel, Deer Creek
Township
1N
Range
7W
Section
33/34
Base
SBB&M

Notice of Determination

Approving Agency
Chaffrey Joint Union High School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print