Laurel Creek Condominiums Project

3 Documents in Project

Summary

SCH Number
2014031010
Lead Agency
Vista, City of (City of Vista)
Document Title
Laurel Creek Condominiums Project
Document Type
NOD - Notice of Determination
Received

Document Description
The California Department of Fish and Wildlife (CDFW) has executed Streambed Alteration Agreement number 1600-2014-0109-R5, pursuant to Section 1602 of the Fish and Game Code to the project Applicant, EHOF Laurel Creek, LLC. The project will construct a new condominium community. The stream through the center of the property will be impacted to establish building pads, roads, parking areas, retaining walls, and a pedestrian bridge. Portions of the stream will be graded and filled, impacting 0.44 acre of the stream. A 12-foot wide access road will be constructed along the eastern edge of stream at the base of the proposed retaining wall. Stream areas avoided by the project will be restored through the removal on non-native vegetation and the establishment of native vegetation.

Contact Information
Kevin Hupf
CDFW South Coastal Region
3883 Ruffin Road
San Diego, CA 92123

858-636-3160

Location

Coordinates
33°11'38.16"N 117°16'26.59"W
Cities
Vista
Counties
San Diego
Cross Streets
Grapevine Rd/Date St.
Total Acres
9.24
Parcel #
166-080-16, -18, -19, -65, -83, 166-110-40, 41
State Highways
Hwy 78
Railways
NCTD Sprinter
Schools
Grapevine ES, Washington MS
Waterways
Buena Vista Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
CDFW South Coastal Region, 3883 Ruffin Road, San Diego, CA 92123

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No