Raley's Dock Replacement and Rice Mill Pier Rehabilitation

8 Documents in Project

Summary

SCH Number
2014022054
Lead Agency
West Sacramento, City of (City of West Sacramento)
Document Title
Raley's Dock Replacement and Rice Mill Pier Rehabilitation
Document Type
NOD - Notice of Determination
Received
Posted
6/29/2015
Present Land Use
RD- Recreation-Parks; RMP- Riverfront Mixed Use /RD-Recreation-Parks; RMP-Waterfront-Planned Development No 41

Document Description
To construct structural repairs to the pier substructure, abutment, and existing piles where needed. New piles may be required if the existing piles do not meet design criteria. A protective rail or fencing system and lighting along the pier perimeter will be installed for public safety. An electrical conduit would be installed at the top of the levee to supply electricity for the pier lighting.

Contact Information
James Hertoa
Central Valley Flood Protection Board
3310 El Camino Avenue, Rm 151
Sacramento, CA 95821

Phone : (916) 574-0651

Location

Coordinates
38°34'59.64"N 121°30'29.08"W
Cities
West Sacramento
Counties
Yolo
Cross Streets
RD: 3rd Street and G Street; RMP: Mill Street and Riverfront Street
Zip
95691
Total Acres
.37
Parcel #
010-422-13, 058-350-06
State Highways
Hwy 80, 5
Railways
Old Sacramento
Schools
WUSD, 5 schools
Waterways
Sacramento River

Notice of Determination

Approving Agency
Central Valley Flood Protection Board
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
3310 El Camino Avenue Rm 151, Sacramento, CA 95821

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search