Kingswood 500 Tank Demolition and Griff Creek Restoration Project, 1600-2014-0078-R2

2 Documents in Project

Summary

SCH Number
2014022039
Lead Agency
North Tahoe Public Utility District
Document Title
Kingswood 500 Tank Demolition and Griff Creek Restoration Project, 1600-2014-0078-R2
Document Type
NOD - Notice of Determination
Received

Document Description
The California Department of Fish and Wildlife is executing Lake or Streambed Alteration Agreement Number 1600-2014-0078-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, North Tahoe Public Utility District. The project will involve the removal of the existing water tank, pump station, and associated above ground infrastructure constructed adjacent to Griff Creek. The tank and pump station will be demolished and removed by truck. The underground piping will be abandoned in place. The large cut and associated cut slope at the location of the water tank will be filled, regraded, and revegetated to match adjacent natural topography.

Contact Information
Patrick Moeszinger
CDFW North Central Region
1701 Nimbus Road, Suite A
Rancho Cordova, CA 95670

916-358-2850

Location

Coordinates
39°14'1.8"N 120°4'55.9"W
Counties
Placer
Cross Streets
Commonweath Dr. and Canterbury Dr.
Zip
96143
Total Acres
14.7
Parcel #
111-160-022; 111-160-021
State Highways
Hwy 267
Railways
No
Airports
No
Schools
Kings Beach ES
Waterways
Lake Tahoe
Township
16N
Range
17E
Section
12
Base
MDB&M
Other Location Info
Kings Beach

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
PO Box 139, Tahoe Vista, CA 96148

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search