Water Treatment Plant Expansion Project

3 Documents in Project

Summary

SCH Number
2014012016
Lead Agency
Rancho Murieta Community Services District
Document Title
Water Treatment Plant Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
8/21/2014
Present Land Use
Rancho Murieta PUD - Sacramento County designations: land use-low Density Residential; zoning - Interim Agricultural (A2)
Document Description
The California Department of Fish and Wildlife is executing Lake or Streambed Alteration Agreement number 1600-2014-0154-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, the Rancho Murieta Community Services District. The project is limited to the addition of approximately 400'x24" diameter raw water pipeline. The pipeline will start at an existing connection to the Lake Chesbro Dam outlet pipe, located in a vault on the southeast corner of the property near Clementia Reservoir, and will extend north and east to the opposite side of the property. The pipeline will be buried underground and will pass through an existing asphalt paved crossing over the top of an existing inlet drainage to Clementia Reservoir near an existing box culvert. In addition to the pipeline, two oak trees approximately 28 and 14" in diameter will be removed from the riparian area of the unnamed stream.

Contact Information

Name
Amy Kennedy
Agency Name
CDFW North Central Region
Contact Types
Lead/Public Agency

Location

Cities
Rancho Murieta
Counties
Sacramento
Cross Streets
project area lies between the end of Clementia Cir. and the Water Treatment Plant
Zip
95683
Total Acres
4.48
Parcel #
various
State Highways
SR 16
Waterways
Chesbro and Clementia Reservoirs

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print