Operation of Crestline Village Water District Zurich Tank Site Project
2 Documents in Project
Summary
SCH Number
2013121061
Lead Agency
Crestline Village Water District
Document Title
Operation of Crestline Village Water District Zurich Tank Site Project
Document Type
NOD - Notice of Determination
Received
Posted
1/12/2015
Present Land Use
Existing water tank; Z: Crest Forest/Rural Living on Private Unincorporated Land; D: Rural living (RL-5)
Document Description
SWRCB, as the responsible agency, will be issuing a water supply permit. The Crestline Village Water District proposed project includes the construction of a new 0.2 million gallon water storage tank (known as Zurich II), which will consist of a 40-foot diameter and 24-foot shell height; the demolition of the existing 0.17 million gallon water storage tank (known as Zurich I), which currently consists of a 36-foot diameter and 24-foot shell height; and the construction of a replacement Zurich I water storage tank which will achieve 0.2 million gallon capacity and will achieve a 40-foot diameter and 24-foot shell height for a combined water storage capacity of 0.4 million gallons for the Zurich Pressure Zone in the Crestline Village Water District service area. The new water storage tanks will be designed and built in compliance with the current standards of the American Water Works Association. New piping interconnecting the tanks will be on site, and no new off-site piping is necessary.
Contact Information
Name
Sean McCarthy
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
San Bernardino
Cross Streets
east of Old Mill Road
Zip
92325
Total Acres
.26
Parcel #
033-80-1121
State Highways
Hwy 138 & 18
Township
2N
Range
4W
Section
22
Base
SBB&M
Other Location Info
Crestline
Notice of Determination
Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.