City of San Luis Obispo General Plan Land Use and Circulation Elements Update

7 Documents in Project

Summary

SCH Number
2013121019
Lead Agency
San Luis Obispo, City of (City of San Luis Obispo)
Document Title
City of San Luis Obispo General Plan Land Use and Circulation Elements Update
Document Type
NOD - Notice of Determination
Received

Document Description
Update of the City's General Plan Land Use and Circulation Elements (LUCE). A Notice of Determination previously filed on September 17, 2014, following the City Council's certification of the EIR and approval of portions of the project on September 16, 2014. The City Council approved remaining portions of the LUCE update project on 12-9-14 and determined that project changes are minor or otherwise reduce project impacts, and there are no changes to surrounding circumstances, or other new information which would trigger the need for supplemental environmental review under PRC 2116 and Guidelines Section 15162. On 12-16-14 the City Council took final action to adopt Ordinance #1610 (2014 Series) establishing an Airport Overlay Zone, Special Focus Overlay Zone, and amending the Zoning designations for Special Planning Areas identified in Chapter 8 of the Land Use and Circulation Element Update Project, which were approved by the Council on September 16, 2014.

Contact Information
Brian Leveille
City of San Luis Obispo
919 Palm Street
San Luis Obispo, CA 93401-3218

805-781-7166

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Regions
City-Wide
Zip
93401
State Highways
Hwy 101
Railways
UPRR
Airports
San Luis Obispo
Schools
SLOCUSD
Waterways
San Luis Creek, Chorro Creek, Prefumo Creek

Notice of Determination

Approving Agency
City of San Luis Obispo
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Community Development Department, 919 Palm Street, City of San Luis Obispo, CA 93401

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search