East Hill Road at Davis Creek Bridge (No. 10C-0113) Replacement Project

3 Documents in Project

Summary

SCH Number
2013112036
Lead Agency
Caltrans 1 (Eureka) (California Department of Transportation, District 1)
Document Title
East Hill Road at Davis Creek Bridge (No. 10C-0113) Replacement Project
Document Type
NOD - Notice of Determination
Received

Document Description
MCDOT will repalce the existing 130 foot long through Pratt truss bridge with a 18 foot wide deck (clear width) that Caltrans classifies as Structurally Deficient and Functionally Obsolete, with a 182 foot long, 40 foot wide, 2-lane, single-span, cast-in-place, pre-stressed concrete box-girder bridge supported on seat type abutments and spread footings with a standard Caltrans concrete barrier Type 80 railings. The vertical profile grade will be similar to the existing to allow adequate freeboard above the 50 and 100-year flood events. The new bridge will be constructed approximatley 70 feet down stream of the existing bridge. The roadway appraches would be widened and realigned to conform to the new bridge. East Hill Road would be realigned to improve the sharp horizontal curve located west of the bridge by increasing the curve radius. Right-of-way acquisition will be needed for this al

Contact Information
Howard N. Dashiell
Mendocino County Department of Transportation
340 Lake Mendocino Drive
Ukiah, CA 95482

707 463 4079

Location

Coordinates
39°23'29"N 123°18'34"W
Cities
Willits
Counties
Mendocino
Cross Streets
East Hill Road at Davis Creek approximately 0.3 mile west of Eastside Road
Zip
95490
Total Acres
2.60
Parcel #
Multiple
State Highways
Hwy 20
Schools
7th Day Adventist
Township
18N
Range
13W
Section
21/28
Base
MDB&M

Notice of Determination

Approving Agency
Mendocino County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
340 Lake Mendocino Drive, Ukiah CA 95482

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search