Interstate 215/Barton Road Interchange Improvement Project

3 Documents in Project

Summary

SCH Number
2013111081
Lead Agency
California Department of Transportation, District 8
Document Title
Interstate 215/Barton Road Interchange Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
3/10/2014
Present Land Use
Transportation, Residential, Commercial
Document Description
The Project will replace existing Barton Road (Rd) Overcrossing, reconstruct and widen Barton Rd, realign existing on-and off-ramps to enhance turning maneuverability and storage capacity, improve local roadways, and modify traffic signals. Within limits of Project, I-215 currently provides 3-lanes in each direction. Barton Rd is a 2-lane roadway west of I-215 and a 4-lane facility with turn lanes at various intersections east of I-215. Barton Rd provides 4 ramps that connection to I-215: southbound on- and off-ramps, and northbound on- and off-ramps. The Project's purpose is to improve operation, increase the capacity, and reduce existing and future congestion at I-215/Barton Rd.

Contact Information

Name
James Shankel
Agency Name
California Department of Transportation, District 8
Contact Types
Lead/Public Agency

Location

Cities
Grand Terrace
Counties
San Bernardino
Cross Streets
I-215, Barton Road
Zip
92313
Total Acres
40
Parcel #
various
State Highways
Hwy 215
Railways
BNSF & UPRR
Schools
4
Waterways
Santa Ana River
Township
1/2S
Range
4W
Section
32/5
Base
SBB&M

Notice of Determination

Approving Agency
California Department of Transportation, District 8
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.