Dillon Road Transmission Main Replacement - Phase 1
2 Documents in Project
Summary
SCH Number
2013111066
Lead Agency
Coachella Valley Water District
(CVWD)
Document Title
Dillon Road Transmission Main Replacement - Phase 1
Document Type
NOD - Notice of Determination
Received
Posted
1/21/2014
Present Land Use
Rural Residential
Document Description
CVWD proposes the construction of a 2.82-mile section of 18 inch diameter domestic water transmission main to replace the existing, 8-inch-diameter, asbestos concrete transmission main that connects CVWD's Booster Station 03603 to Booster Station 04701 along Dillon Road between the communities of Sky Valley and Indio Hills, Riverside County. The proposed ductile iron pipeline will be constructed immediately adjacent to the existing, deteriorated pipeline within the Riverside County right-of-way along the north side of Dillon Road. Booster Station 03603 is located on the north side of Dillon Road approximately 1,500 feet NW of Thousand Palms Canyon Road; Booster Station 04701 is located on the South side of Dillon Road approximately 750 feet SE of Western Avenue.
Contact Information
Name
J.M. Barrett
Agency Name
Coachella Valley Water District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Indio
Counties
Riverside
Cross Streets
Western Avenue/Dillon Road
Zip
92241
Total Acres
.5
Parcel #
various
Township
3,4S
Range
6,7E
Section
varies
Base
SBB&M
Other Location Info
Sky Valley
Notice of Determination
Approving Agency
Coachella Valley Water District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.