Amendment to City of Encinitas Opportunistic Beach Fill Program

5 Documents in Project

Summary

SCH Number
2013111057
Lead Agency
City of Encinitas
Document Title
Amendment to City of Encinitas Opportunistic Beach Fill Program
Document Type
NOD - Notice of Determination
Received
Posted
10/20/2014
Present Land Use
Open Space
Document Description
Amend the City of Encinitas' (City) existing Opportunistic Beach Fill Program to include two new receiving beaches, Leucadia Beach and Cardiff Beach, to allow streamlined approval of projects proposing placement of beach compatible materials derived from opportunistic sources (e.g., upland construction projects, wetland restoration, dredging). Addition of these beaches will allow flexibility in placement locations to address areas of localized erosion and/or minimize haul or dredge distances from a given sediment source. The additional sites are: 1) Leucadia Beach between Range Street and Diana Street; and 2) Cardiff Beach in the vicinity of Restaurant Row. The State Lands Commission action is issuance of a 5-year General Lease - Public Agency Use to the City of Encinitas for deposition of up to a maximum of 117,000 cubic yards (cy) of sand annually at Batiquitos Beach, up to a maximum of 105,000 cy of sand annually at Moonlight State Beach, up to a maximum of 132,000 cy of sand annually at Leucadia State Beach, and up to a maximum of 101,000 cy of sand annually at Cardiff State Beach.

Contact Information

Name
Jennifer Lucchesi
Agency Name
California State Lands Commission
Contact Types
Lead/Public Agency

Location

Cities
Encinitas
Counties
San Diego
Cross Streets
C. Coast Highway 101 & Phoebe St.; S. Coast Highway 101 and Cardiff State Beach
Zip
92024
Total Acres
27
State Highways
SR 21
Railways
NCTD
Airports
No
Schools
Multiple
Waterways
Pacific Ocean
Township
13S
Range
4W
Section
4

Notice of Determination

Approving Agency
California State Lands Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print