Mission Creek (Zone 6, Line L) Restoration Project

3 Documents in Project

Summary

SCH Number
2013102049
Lead Agency
Alameda County Water District (ACWD)
Document Title
Mission Creek (Zone 6, Line L) Restoration Project
Document Type
NOD - Notice of Determination
Received
Posted
3/17/2014
Present Land Use
Park Open Space, O-S District
Document Description
The ACFCWCD is proposing to increase flood conveyance and restore and enhance aquatic habitats along Zone 6 Line L flood control channel (Mission Creek) between Lemos Lane and the UPRR on the west side of the Fremont Park Golf Club in Alameda County, CA. The project's objectives are to increase channel flood conveyance to contain the 100-year design flow, stabilize eroded slopes using biotechnical bank stabilization, improve riparian habitat function, and replace exotic plant species with native ones. The preliminary designs include widening and meandering portions of the existing creek channel, creating low flow channels, removing and replacing existing culverts and pedestrian bridges and paths, replacing gabion walls with low retaining walls, and constructing berms and bank stabilization features.

Contact Information

Name
Jim Browne
Agency Name
Alameda County Flood Control & Water Conservation District
Contact Types
Lead/Public Agency

Location

Cities
Fremont
Counties
Alameda
Cross Streets
Lemos Lane/Chiltern Drive
Zip
94539
Railways
SPRR, WPRR
Schools
Brier ES, CA
Waterways
Hetch Hetchy Aqueduct, Lake Elizabeth
Township
4S
Range
1W
Section
27
Base
MDB&M

Notice of Determination

Approving Agency
Alameda County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print