Pacific Gas & Electric Company Contra Costa-Moraga 230 Kilovolt (Kv) Reconductoring Project: Galindo Creek Tributary Alterations

4 Documents in Project

Summary

SCH Number
2013102015
Lead Agency
State Water Resources Control Board
Document Title
Pacific Gas & Electric Company Contra Costa-Moraga 230 Kilovolt (Kv) Reconductoring Project: Galindo Creek Tributary Alterations
Document Type
NOD - Notice of Determination
Received
Posted
8/11/2014
Present Land Use
Various, including industrial, open space, commercial, residential, agricultural, and utility
Document Description
The project is limited to two activities: a temporary road crossing structure across an unnamed ephemeral channel to facilitate construction equipment access and installation of a temporary protection measure (Crossing Structure) within the bed and bank of an unnamed ephemeral channel. Project activities are part of a larger project that includes reconductoring of the existing Contra Costa-Moraga 230 kilovolt (kV) transmission line between Contra Costa Power Plant Substation and the Moraga Substation.

Contact Information

Name
Serge Glushkoff
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Antioch, Clayton, Concord, Walnut Creek
Counties
Contra Costa
Cross Streets
Various
Zip
Various
Total Acres
37
Parcel #
051031015
State Highways
SR 4, 24
Railways
Burlington Northern
Airports
No
Schools
Various
Waterways
San Joaquin River, Sherman Lake, Mayberry Slough
Township
2N
Range
2E
Section
16
Base
MDB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print