Draft Remedial Action Plan - Former Fresno 1 Manufactured Gas Plant

2 Documents in Project

Summary

SCH Number
2013101028
Lead Agency
Department of Toxic Substances Control
Document Title
Draft Remedial Action Plan - Former Fresno 1 Manufactured Gas Plant
Document Type
NOD - Notice of Determination
Received
Posted
12/12/2013
Present Land Use
Heavy Industrial
Document Description
The Dept. of Toxic Substances Control (DTSC) has approved a Remedial Action Plan (RAP) pursuant to regulatory authority granted under Chapter 6.8, Division 20, California Health and Safety Code (H&SC) on the PG&E Former Fresno-1 Manufactured Gas Plant (MGP) site located at 211 North Thorne Avenue, Fresno, CA in Fresno County. The RAP will address impacts to soils gases from previous operations on the Site. The remedial activities will involve excavation and disposal at an off-site permitted facility of ~37,400 cubic yards or ~1,400 truckloads (2,800 round trips) of contaminated soils that are highly impacted by polycyclic aromatic hydrocarbons (PAHs), benzene, arsenic, lead, and petroleum hydrocarbons. The remaining soil impacted areas will be capped and land use covenants will be placed upon them. Additionally, there will be ~the same amount of clean backfill imported from a local quarry located in Friant, CA that is ~22.8 miles southeast of the Site. The imported fill will be tested for contaminants in accordance with DTSCs October 2001 Imported Advisory on Clean Fill Material. The remediation activities will occur in three phases, with each phase taking an estimated four to six months to complete. The three phases will start in the year 2015 and end in 2017.

Contact Information

Name
Jeff Gymer
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Fresno
Counties
Fresno
Cross Streets
Thorne/Fruit
Zip
93706
Total Acres
11.8
Parcel #
458-04-17, 18, 05
State Highways
Hwy 99
Railways
UPRR
Airports
Chandler Airfield
Schools
Muir ES
Waterways
Herndon Canal
Township
14S
Range
49W
Section
5
Base
MDB&M

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print